Kraftnod Platform
Control plane for distributed energy & compute
← Sites
Simulated
Last 30 days · simulated
Site · SE4
SITE-SE4-00603
Example Fastigheter AB – Växjö. The control plane steers the whole site — not just the GPUs.
Location
Växjö
Grid area SE4
Grid connection
250 A
112 kW available
Internet
Fiber 10 Gbit
Site owner
Example Fastigheter AB
Agent AGENT-SE4-00603
Site topology
Grid · import 78.7 kW
SITE-SE4-00603
GPU CLUSTER
4 GPU
RUN · 2.7 kW
BUILDING LOAD
50 kW
BASELINE · 50 kW
BATTERY
200 kWh
IDLE · 0 kW
EV CHARGER
8 chargers
LIMIT · 26 kW
Assets and ownership
| Asset | Type | Make / model | Capacity | Power | Owner | Status | Telemetry | Markets |
|---|---|---|---|---|---|---|---|---|
| SITE-SE4-00603-GPU | GPU_CLUSTER | NVIDIA RTX PRO 6000 Blackwell | 4 GPU | 3 kW | Finance Partner Fund I | ONLINE | powerKw 1.1 · utilPct 30 · tempC 18 · inUse 1 | COMPUTE |
| SITE-SE4-00603-GRID | GRID_CONNECTION | DSO 250 A main fuse | 173 kW | 173 kW | Example Fastigheter AB | ONLINE | importKw 0 | — |
| SITE-SE4-00603-LOAD | BUILDING_LOAD | — Building load | 50 kW | 50 kW | Example Fastigheter AB | ONLINE | powerKw 50 | PEAK_REDUCTION |
| SITE-SE4-00603-BAT | BATTERY | BYD 200 kWh LFP | 200 kWh | 100 kW | Example Fastigheter AB | ONLINE | socPct 54 · powerKw 0 · mode idle | FCR, AFRR, MFRR, PEAK_REDUCTION, SPOT_ENERGY |
| SITE-SE4-00603-EV | EV_CHARGER | Easee 8 × 11 kW | 8 chargers | 88 kW | Example Fastigheter AB | ONLINE | powerKw 26 | PEAK_REDUCTION, MFRR |
Each asset can have its own owner. Control plane: Kraftnod.
Maximize value per connected kW
Kraftnod Optimizer — decision
Available site power: 62 kW
Option ARun compute6.21 SEK/kWh
Kraftnod Marketplace net 14.54 SEK/GPU-h × demand 35%
Option BCharge battery0.99 SEK/kWh
Shift to evening peak 1.88 SEK/kWh, 88% round-trip
Option CReserve battery for FCR1.93 SEK/kWh
FCR 483 SEK/MW/h, 0.25 h energy reserve
Option DIdle / grid only0.00 SEK/kWh
Baseline
DecisionRUN COMPUTE
- Spot now
- 0.75 SEK/kWh
- Evening peak
- 1.88 SEK/kWh
- Battery SOC
- 54%
- Grid limit
- 112 kW
- Building load
- 50 kW
Dispatch
| Asset | Action | Power |
|---|---|---|
| GPU cluster | RUN | 2.7 kW |
| Building load | BASELINE | 50 kW |
| Battery | IDLE | 0 kW |
| EV charging | LIMIT | 26 kW |
| Grid | IMPORT | 78.7 kW |
Site value
Compute9 044 SEK
Battery flex28 971 SEK
Peak reduction6 599 SEK
Solar optimization0 SEK
Total site value44 614 SEK / month
Energy cost−400 SEK
Net site value44 214 SEK
