Kraftnod Platform
Control plane for distributed energy & compute
← Sites
Simulated
Last 30 days · simulated
Site · SE3
SITE-SE3-00757
Industripark Väst AB – Jönköping. The control plane steers the whole site — not just the GPUs.
Location
Jönköping
Grid area SE3
Grid connection
125 A
56 kW available
Internet
Fiber 10 Gbit
Site owner
Industripark Väst AB
Agent AGENT-SE3-00757
Site topology
Grid · import 93.7 kW
SITE-SE3-00757
GPU CLUSTER
4 GPU
RUN · 2.7 kW
BUILDING LOAD
65 kW
BASELINE · 65 kW
BATTERY
400 kWh
IDLE · 0 kW
SOLAR
40 kWp
IDLE · 0 kW
EV CHARGER
8 chargers
LIMIT · 26 kW
Assets and ownership
| Asset | Type | Make / model | Capacity | Power | Owner | Status | Telemetry | Markets |
|---|---|---|---|---|---|---|---|---|
| SITE-SE3-00757-GPU | GPU_CLUSTER | NVIDIA RTX PRO 6000 Blackwell | 4 GPU | 3 kW | Kraftnod AssetCo 02 | ONLINE | powerKw 1.4 · utilPct 42 · tempC 21 · inUse 2 | COMPUTE |
| SITE-SE3-00757-GRID | GRID_CONNECTION | DSO 125 A main fuse | 86 kW | 86 kW | Industripark Väst AB | ONLINE | importKw 0 | — |
| SITE-SE3-00757-LOAD | BUILDING_LOAD | — Building load | 65 kW | 65 kW | Industripark Väst AB | ONLINE | powerKw 65 | PEAK_REDUCTION |
| SITE-SE3-00757-BAT | BATTERY | Dyness 400 kWh LFP | 400 kWh | 200 kW | Industripark Väst AB | ONLINE | socPct 52 · powerKw 0 · mode idle | FCR, AFRR, MFRR, PEAK_REDUCTION, SPOT_ENERGY |
| SITE-SE3-00757-PV | SOLAR | Solis 40 kWp array | 40 kWp | 40 kW | Industripark Väst AB | ONLINE | powerKw 0 | SPOT_ENERGY |
| SITE-SE3-00757-EV | EV_CHARGER | Easee 8 × 11 kW | 8 chargers | 88 kW | Industripark Väst AB | ONLINE | powerKw 40 | PEAK_REDUCTION, MFRR |
Each asset can have its own owner. Control plane: Kraftnod.
Maximize value per connected kW
Kraftnod Optimizer — decision
Available site power: 0 kW
Option ARun compute6.42 SEK/kWh
Kraftnod Marketplace net 14.7 SEK/GPU-h × demand 35%
Option BCharge battery0.71 SEK/kWh
Shift to evening peak 1.35 SEK/kWh, 88% round-trip
Option CReserve battery for FCR1.68 SEK/kWh
FCR 420 SEK/MW/h, 0.25 h energy reserve
Option DIdle / grid only0.00 SEK/kWh
Baseline
DecisionRUN COMPUTE
- Spot now
- 0.54 SEK/kWh
- Evening peak
- 1.35 SEK/kWh
- Battery SOC
- 52%
- Grid limit
- 56 kW
- Building load
- 65 kW
Dispatch
| Asset | Action | Power |
|---|---|---|
| GPU cluster | RUN | 2.7 kW |
| Building load | BASELINE | 65 kW |
| Battery | IDLE | 0 kW |
| Solar | IDLE | 0 kW |
| EV charging | LIMIT | 26 kW |
| Grid | IMPORT | 93.7 kW |
Site value
Compute17 453 SEK
Battery flex51 223 SEK
Peak reduction13 416 SEK
Solar optimization528 SEK
Total site value82 620 SEK / month
Energy cost−338 SEK
Net site value82 282 SEK
