Kraftnod – Nordic Distributed Data Center
Kraftnod Platform
Control plane for distributed energy & compute
Demo · simulated data
← Sites
Site · SE2

SITE-SE2-00673

Residence Sundsvall. The control plane steers the whole site — not just the GPUs.

Location
Sundsvall
Grid area SE2
Grid connection
25 A
11 kW available
Internet
Fiber 1 Gbit
Site owner
Privat host
Agent AGENT-SE2-00673

Site topology

Grid · import 7.4 kW
SITE-SE2-00673
GPU CLUSTER
2 GPU
RUN · 1.4 kW
BUILDING LOAD
3 kW
BASELINE · 3 kW
BATTERY
15 kWh
IDLE · 0 kW
SOLAR
8 kWp
IDLE · 0 kW
EV CHARGER
1 chargers
LIMIT · 3 kW

Assets and ownership

AssetTypeMake / modelCapacityPowerOwnerStatusTelemetryMarkets
SITE-SE2-00673-GPUGPU_CLUSTERNVIDIA RTX 6000 Ada2 GPU1.5 kWHost-ownedMAINTENANCEpowerKw 0.2 · utilPct 0 · tempC 17 · inUse 0COMPUTE
SITE-SE2-00673-GRIDGRID_CONNECTIONDSO 25 A main fuse17 kW17 kWPrivat hostONLINEimportKw 0—
SITE-SE2-00673-LOADBUILDING_LOAD— Building load3 kW3 kWPrivat hostONLINEpowerKw 3PEAK_REDUCTION
SITE-SE2-00673-BATBATTERYDyness 15 kWh LFP15 kWh8 kWPrivat hostONLINEsocPct 51 · powerKw 0 · mode idleFCR, AFRR, MFRR, PEAK_REDUCTION, SPOT_ENERGY
SITE-SE2-00673-PVSOLARSMA 8 kWp array8 kWp8 kWPrivat hostONLINEpowerKw 0SPOT_ENERGY
SITE-SE2-00673-EVEV_CHARGERZaptec 1 × 11 kW1 chargers11 kWPrivat hostONLINEpowerKw 3PEAK_REDUCTION, MFRR

Each asset can have its own owner. Control plane: Kraftnod.

Maximize value per connected kW

Kraftnod Optimizer — decision

Simulated
Available site power: 8 kW
Option ARun compute3.72 SEK/kWh
Kraftnod Marketplace net 8.66 SEK/GPU-h × demand 34%
Option BCharge battery0.32 SEK/kWh
Shift to evening peak 0.60 SEK/kWh, 88% round-trip
Option CReserve battery for FCR1.51 SEK/kWh
FCR 378 SEK/MW/h, 0.25 h energy reserve
Option DIdle / grid only0.00 SEK/kWh
Baseline
DecisionRUN COMPUTE
Spot now
0.24 SEK/kWh
Evening peak
0.60 SEK/kWh
Battery SOC
51%
Grid limit
11 kW
Building load
3 kW

Dispatch

AssetActionPower
GPU clusterRUN1.4 kW
Building loadBASELINE3 kW
BatteryIDLE0 kW
SolarIDLE0 kW
EV chargingLIMIT3 kW
GridIMPORT7.4 kW

Site value

Last 30 days · simulated
Compute0 SEK
Battery flex1 917 SEK
Peak reduction559 SEK
Solar optimization111 SEK
Total site value2 587 SEK / month
Energy cost−−0 SEK
Net site value2 587 SEK